Work/Rate/Time problems on the GMAT

GMAT MBA & Business

Statistical Mediation & Moderation in Psychological Research (12)For many people studying for the GMAT, Work/Rate/Time problems prove to be a particularly sore spot on the Quantitative Reasoning section. In this lesson, we will learn an efficient and effective way to tackle these problem types algebraically.

Work/Rate/Time problems are based on one simple formula.

Screen Shot 2020-05-25 at 2.26.30 PM

 

In this equation, W is the amount of work done/produced, r is the rate at which the work is completed, and t is the time in which the work is completed. In most cases, we will be able to determine two of these values and use algebra to solve for the third value. There is also an important point to make about the rate:

Screen Shot 2020-05-25 at 2.27.11 PM

 

With these equations, let us look at a few examples.

Example 1: Multiple Workers Working at Different Rates

Rachel can build a house in 3 days, while Seth can build a house in 4 days. If Rachel and Seth work together, how long will it take for them to build 7 houses?

First, we need to calculate Rachel and Seth’s unit rates in houses per day.

Screen Shot 2020-05-25 at 2.28.59 PM

 

Once we have two units rates, we add them together to find a combined rates.

 

Screen Shot 2020-05-25 at 2.29.39 PM
 
Now use the equation W = rt, plugging in y for W, 7/12 for r, and solving for t:
 

We solve algebraically for the missing value of t. It will take Seth and Rachel 12 days to build the seven houses. Now, let us move onto another version of this problem type.

Example 2: Multiple Workers Working at a Constant Rate

5 identical machines working at a constant rate can produce 12 widgets in 2 hours. How long will it take for 8 machines to produce 24 widgets?

For this problem, we will need a slight variation on our basic formula.

Screen Shot 2020-05-25 at 2.31.46 PM

 

Here, the variable N will refer to the number of machines, whereas r still represents the rate of one machine. Let us use this formula with the given initial information, plugging in 12 widgets for W, 5 machines for N, and 2 hours for t. We will solve for the missing variable r.

Screen Shot 2020-05-25 at 2.33.04 PM

Now, we know the rate of one machine. What if 8 machines work together to make 24 widgets?

We use the W = Nrt equation again, this time plugging in 24 for W, 6/5 for r, 8 for N, and solving for t.

 

And we have an answer! It will take 2.5 hours for 8 machines to produce 24 widgets.

How does this approach apply to more difficult GMAT problems?

More difficult Work/Rate/Time problems apply the same principle but may require you to solve a system of equations and deal with more unknown values. To demonstrate, let us look at an actual GMAT problem:

Official Guide 2018: Problem Solving #113 from p. 162 of GMAT Official Guide 2018 (copyright 2017 by the Graduate Management Admission Council, published by John Wiley & Sons, Inc., Hoboken, NJ)

Three printing presses, R, S, and T working together at their respective constant rates, can do a certain printing job in 4 hours. S and T, working together at their respective constant rates, can do the same job in 5 hours. How many hours would it take R, working alone at its constant rate, to do the same job?

(A) 8

(B) 10

(C) 12

(D) 15

(E) 20

We begin with writing an algebraic representation of the first sentence “Three printing presses, R, S, and T working together at their respective constant rates, can do a certain printing job in 4 hours.” Our work W will be 1 job, our rate will be R + S + T, and our time t will be 4.

Screen Shot 2020-05-25 at 2.36.21 PM

Now, we translate the second statement, “S and T, working together at their respective constant rates, can do the same job in 5 hours,” in the same way.

Screen Shot 2020-05-25 at 2.37.10 PM

We are looking for how long it will take printing press R to complete the job by itself. We must find out the individual rate of printing press R. We can do this through substitution.

Screen Shot 2020-05-25 at 2.37.50 PM
Now that we know the individual rate for R, we need to find the time needed for one job. W is still 1, r is 1/20, and t is unknown.
 

We have our answer! It will take (E) 20 hours for printing press R to complete 1 job.

In conclusion

There are a ton of concepts on the GMAT quant section, but certain problem types come up repeatedly. Work/Rate/Time problems comprise just one of these problem types, but if you learn how to tackle Work/Rate/Time problems, you can devote more energy to other questions on the exam. As always, be sure to keep track of any GMAT problems you miss during practice, and look for patterns in the question types you miss the most frequently – this is the best way to study and improve your score.

Comments

topicTopics
academics study skills MCAT medical school admissions SAT expository writing college admissions English MD/PhD admissions strategy writing LSAT GMAT GRE physics chemistry math biology graduate admissions academic advice ACT interview prep law school admissions test anxiety language learning premed MBA admissions career advice personal statements homework help AP exams creative writing MD study schedules test prep computer science Common Application summer activities history mathematics philosophy organic chemistry secondary applications economics supplements research 1L PSAT admissions coaching grammar law psychology statistics & probability legal studies ESL CARS SSAT covid-19 dental admissions logic games reading comprehension engineering USMLE calculus PhD admissions Spanish mentorship parents Latin biochemistry case coaching verbal reasoning DAT English literature STEM excel medical school political science skills AMCAS French Linguistics MBA coursework Tutoring Approaches academic integrity chinese letters of recommendation Anki DO Social Advocacy admissions advice algebra art history artificial intelligence astrophysics business cell biology classics diversity statement gap year genetics geometry kinematics linear algebra mechanical engineering mental health presentations quantitative reasoning study abroad technical interviews time management work and activities 2L DMD IB exams ISEE MD/PhD programs Sentence Correction adjusting to college algorithms amino acids analysis essay athletics business skills careers cold emails data science dental school finance first generation student functions graphing information sessions international students internships logic networking poetry resume revising science social sciences software engineering tech industry trigonometry writer's block 3L AAMC Academic Interest EMT FlexMed Fourier Series Greek Health Professional Shortage Area Italian Lagrange multipliers London MD vs PhD MMI Montessori National Health Service Corps Pythagorean Theorem Python Shakespeare Step 2 TMDSAS Taylor Series Truss Analysis Zoom acids and bases active learning architecture argumentative writing art art and design schools art portfolios bacteriology bibliographies biomedicine brain teaser campus visits cantonese capacitors capital markets central limit theorem centrifugal force chemical engineering chess chromatography class participation climate change clinical experience community service constitutional law consulting cover letters curriculum dementia demonstrated interest dimensional analysis distance learning econometrics electric engineering electricity and magnetism escape velocity evolution executive function freewriting genomics harmonics health policy history of medicine history of science hybrid vehicles hydrophobic effect ideal gas law immunology induction infinite institutional actions integrated reasoning intermolecular forces intern investing investment banking lab reports linear maps mandarin chinese matrices mba medical physics meiosis microeconomics mitosis mnemonics music music theory nervous system neurology neuroscience object-oriented programming office hours operating systems